Free MHIC practice test (15 sample questions)
Format figures below are from the PSI candidate bulletin for Maryland Home Improvement (updated October 10, 2025). Statute citations are to the public Maryland Code. Always check the current PSI bulletin and the cited section before you test or apply. This site is a study aid. It is not affiliated with or endorsed by the Maryland Home Improvement Commission, the Maryland Department of Labor, PSI, or NASCLA. These are not actual exam questions, and we do not guarantee that you will pass.
These 15 questions are a free sample from our bank of original practice items. They cover Maryland home improvement law, the Door-to-Door Sales Act, labor, safety, and estimating. Each item includes an explanation and a citation to the public section it was written from.
You can also take the same 15 questions as an untimed quiz on the home page, with instant feedback after each answer.
15 free sample questions are published here. The full bank is larger and is unlocked with a 90-day pass. These are not questions from the official exam.
1. Home Improvement Law
A builder signs an agreement to construct a brand-new single-family house on a vacant lot. Under the Maryland Home Improvement Law, this work is:
Answer and explanation
The definition of home improvement specifically excludes construction of a new home.
Source: BR §8-101
2. Home Improvement Law
At any one time, a licensed salesperson may sell on behalf of no more than:
Answer and explanation
A salesperson may not sell for more than 2 licensed contractors at the same time.
Source: BR §8-310
3. Home Improvement Law
At a hearing on a Guaranty Fund claim, the burden of proof is on:
4. Home Improvement Law
Which factor must the Commission consider in setting a civil penalty?
Answer and explanation
Listed factors: seriousness, good faith, previous violations, harm, the violator's assets, and other relevant factors.
Source: BR §8-620
5. Door-to-Door Sales
Under the Maryland Door-to-Door Sales Act, a door-to-door sale must have a purchase price of at least:
Answer and explanation
The Act applies to consumer sales of $25 or more solicited in person away from the seller's place of business.
Source: CL §14-301
6. Door-to-Door Sales
A buyer cancels and makes the delivered goods available, but the seller does not pick them up. The buyer may keep or dispose of the goods after:
Answer and explanation
The required notice says the buyer may keep or dispose of goods not picked up within 20 days.
Source: CL §14-302
7. Labor & Employment
Under the federal Fair Labor Standards Act, a covered non-exempt employee must be paid overtime for hours over 40 in a workweek at a rate of at least:
Answer and explanation
FLSA requires at least one and one-half times the regular rate for hours over 40.
Source: 29 U.S.C. §207(a)(1)
8. Safety
Under federal OSHA construction rules, workers on a walking or working surface with an unprotected edge must be protected from falls when they are at least how high above a lower level?
Answer and explanation
The general construction fall-protection trigger height is 6 feet.
Source: 29 CFR §1926.501(b)(1)
9. Estimating & Business Math
A gable roof has two rectangular planes, each 30 ft by 20 ft. How many roofing squares are needed before waste?
Answer and explanation
Each plane is 600 sq ft, so the total is 1,200 sq ft. One square is 100 sq ft, giving 12 squares.
Source: Worked calculation (original)
10. Home Improvement Law
Under §8-302, the competency part of the examination:
Answer and explanation
The competency part of the examination may be oral or written.
Source: BR §8-302(f)(3)
11. Home Improvement Law
For MHIC hearing regions, Montgomery County is grouped with:
Answer and explanation
One region includes Montgomery and Prince George's counties.
Source: BR §8-312(e)
12. Home Improvement Law
A contractor fully repays the Fund. Does that cancel a separate disciplinary action?
Answer and explanation
Reimbursement by itself does not nullify or modify the effect of a disciplinary proceeding.
Source: BR §8-411(c)
13. Home Improvement Law
A contract says it is "subject to approval by the contractor." COMAR requires the contractor to approve or disapprove within:
Answer and explanation
Approval or disapproval must be made, and the owner informed in writing, within 10 working days.
Source: COMAR 09.08.01.15(A)
14. Door-to-Door Sales
A 70-year-old signs a door-to-door home improvement contract on Friday, November 6, 2026. Skipping Sundays and Veterans' Day (Wed, Nov 11), the 7th business day is:
Answer and explanation
Sat 7, Mon 9, Tue 10, Thu 12, Fri 13, Sat 14, Mon 16 (Sun 8, Wed 11 and Sun 15 skipped).
Source: CL §§14-301(b), 14-302.1
15. Estimating & Business Math
How many board feet are in ten 2 x 6 boards, each 12 ft long (nominal dimensions)?
Answer and explanation
Board feet = (thickness x width x length in ft) / 12 = (2 x 6 x 12) / 12 = 12 per board; x 10 = 120.